License Instrument received

November 29, 2007

Magnox North begin Shadow Working

Magnox Electric has received a Licence Instrument from the Nuclear Installations Inspectorate (NII), enabling Magnox North and Magnox South to enter a period of Shadow Working.

September 24, 2007

Oldbury's Reactor 2 returns to service

Oldbury Power Station has started generating electricity again after successfully transferring steam to its number one turbine.

September 20, 2007

Restart of generation at Oldbury

Nuclear Engineering International have carried a short news item on the restart of generation at Oldbury.

September 13, 2007

Decommissioning progress at Trawsynydd

Radwaste Solutions, the Journal of the American Nuclear Society, recently published an article about decommissioning progress at Trawsfynydd.