Site History

WelshCYM | EnglishENG

Built in the late 1950s/early 1960s, Trawsfynydd started service in 1965 and generated electricity for 26 years before it reached the end of its service life in 1991. Trawsfynydd was the first inland civil Magnox nuclear power station and drew its cooling water, at the rate of 35 million gallons an hour, from the man-made Trawsfynydd lake, originally built in the 1920s as part of a hydro-electric project at Maentwrog and still in use today.

Site operations

1965-1989: Central Electricity Generating Board (CEGB)

1989-1994: Nuclear Electric plc (following the part privatisation of the CEGB)

1994-1998: Magnox Electric plc (following the transfer of the AGR and PWR nuclear power stations to British Energy plc)

1998-2004: British Nuclear Fuels plc

2004 to date: The Nuclear Decommissioning Authority (following the restructuring of the UK nuclear industry and transfer of all UK nuclear legacy to the NDA)

 

Significant Dates

 
 
1959 - 1965      Construction of the site
 
1965 -1991       Generation
 
1968                   Official opening by James Griffiths, Secretary of State for Wales
 
1991                   Generation ceased       
       
1993                   Site officially closed.
 
1993 - 1995       De-fuelling
 
1995                    De-planting and decommissioning
 
1998                    Ponds drained
 
2003                    Demolition of Turbine Hall
 
2005                    MAC (North) Vault emptied, FED (South) Recovery commences
 
2005                    Bailey bridge & Pontoon removed
 
2005                    Cold Water Pumphouse decommissioned & demolished
 
2005                    Construction of ILW Store commences           
 
2005                    Removal of first boiler sections R1 (North)
 
2006                    Ponds Scabbling commences
                             Completion of Reactor 1 (North) Boiler Section Removal
                             Site awarded 3rd consecutive RoSPA Gold Medal
 
2006                    Active Waste Vault B4 emptied
 
2006                    First liner of Sludge exported from the Main Sludge Vault
 
2006                    Site End State Consultation Commences
 
2006                    Bulk retrieval of Resin from Resin Vault 1 completed                                             
 
2006                     Site End State Report delivered to the NDA
 
2007                     Active Waste Vault B3 emptied.
 
2007                     Completion of Hot Gas Ducts Removal
 
2007                     Removal of first boiler sections Reactor 2 (South)
 
2007                     Boiler section removal in Reactor2 South is now complete
 
2007                     Completion of the Intermediate Level Waste Store
 
2008                     Work commenced to install Capping Roof on Reactor 2 Charge Hall
 
2008                     Completion of recovery of the first Intermediate Level Waste (ILW) stream in the UK - MAC
                                                                                                           
2009                     Completion of Partial Relocation of Primary Circuit Components (PRPCC)